PERMANENT RULES
COMMISSION
1 STATUTORY OR OTHER AUTHORITY: The Washington utilities and transportation commission (commission) takes this action under Notice No. WSR 08-07-080, filed with the code reviser on March 19, 2008. The commission brings this proceeding pursuant to RCW 80.01.040, 80.04.060, and 81.88.040.
2 STATEMENT OF COMPLIANCE: This proceeding complies with the Administrative Procedure Act (chapter 34.05 RCW), the State Register Act (chapter 34.08 RCW), the State Environmental Policy Act of 1971 (chapter 43.21C RCW), and the Regulatory Fairness Act (chapter 19.85 RCW).
3 DATE OF ADOPTION: The commission adopts this rule on the date this order is entered.
4 CONCISE STATEMENT OF PURPOSE AND EFFECT OF THE RULE: RCW 34.05.325(6) requires the commission to prepare and publish a concise explanatory statement about an adopted rule. The statement must identify the commission's reasons for adopting the rule, describe the differences between the version of the proposed rules published in the register and the rules adopted (other than editing changes), summarize the comments received regarding the proposed rule changes, and state the commission's responses to the comments reflecting the commission's consideration of them.
5 To avoid unnecessary duplication in the record of this docket, the commission designates the discussion in this order, including appendices, as its concise explanatory statement, supplemented where not inconsistent by the staff memoranda preceding the filing of the CR-102 proposal and the adoption hearing. Together, these documents provide a complete but concise explanation of the agency actions and its reasons for taking those actions.
6 REFERENCE TO AFFECTED RULES: This order amends the following sections of the Washington Administrative Code: WAC 480-75-100 Definitions, 480-75-200 Application of rules, 480-75-210 Additional requirements, 480-75-240 Annual pipeline safety fee methodology, 480-75-250 Civil penalty for violation of chapter 81.88 RCW, 480-75-260 Exemption for rules in chapter 480-75 WAC, 480-75-270 Damage prevention, 480-75-300 Leak detection, 480-75-310 Geological considerations, 480-75-320 Overpressure protection, 480-75-330 Overfill protection, 480-75-340 Cathodic protection test station location, 480-75-350 Design specifications for new pipeline, 480-75-360 Class locations, 480-75-370 Design factor (F) for steel pipe, 480-75-380 Location of pump stations and breakout tanks for pipelines, 480-75-390 Valve spacing and rapid shutdown, 480-75-400 Backfill and bed requirements, 480-75-410 Coatings, 480-75-420 Hydrostatic test requirements, 480-75-430 Welding procedures, 480-75-440 Pipeline repairs, 480-75-450 Construction specifications, 480-75-460 Welding inspection requirements, 480-75-500 Moving and lowering hazardous liquid pipelines, 480-75-510 Remedial action for corrosion deficiencies, 480-75-520 Inspections during excavation, 480-75-530 Right of way inspections, 480-75-540 Pipeline markers and above ground facilities, 480-75-550 Change in class locations, 480-75-600 Maps, drawings, and records of hazardous liquid facilities, 480-75-610 Reporting requirements for proposed construction, 480-75-620 Pressure testing reporting requirements, 480-75-630 Incident reporting, 480-75-640 Depth-of-cover survey, 480-75-650 Annual reports, 480-75-660 Procedural manual for operations, maintenance, and emergencies, and 480-75-999 Adoption by reference.
7 PREPROPOSAL STATEMENT OF INQUIRY AND ACTIONS THEREUNDER: The commission filed preproposal statements of inquiry (CR-101) on July 26, 2007, at WSR 07-16-059 and on October 24, 2007, at WSR 07-21-146.
8 The statements advised interested persons that the commission was considering entering a rule making for chapter 480-75 WAC, Hazardous liquid, gas, oil and petroleum pipeline companies -- Safety, amending the rules to reflect changes in Title 81 RCW resulting from the passage of SSB 5225 during the 2007 legislative session. The commission also informed persons of this inquiry by providing notice of the subject and the CR-101 to everyone on the commission's list of persons requesting such information pursuant to RCW 34.05.320(3) and by sending notices to all regulated pipeline companies and the commission's list of regulatory attorneys. Pursuant to the notices, the commission received written comments.
9 NOTICE OF PROPOSED RULE MAKING: The commission filed a notice of proposed rule making (CR-102) on March 19, 2008, at WSR 08-07-080. The commission scheduled this matter for oral comment and adoption under Notice No. WSR 08-07-080 at 1:30 p.m., Thursday, May 15, 2008, in the Commission's Hearing Room, Second Floor, Richard Hemstad Building, 1300 South Evergreen Park Drive S.W., Olympia, WA. The notice provided interested persons the opportunity to submit written comments to the commission.
10 WRITTEN COMMENTS: The commission received no written comments on the proposed rules.
11 RULE-MAKING HEARING: The commission considered the proposed rules for adoption at a rule-making hearing on May 15, 2008, before Chairman Mark H. Sidran, Commissioner Patrick J. Oshie, and Commissioner Philip B. Jones. No person made oral comments.
12 COMMISSION ACTION: After considering all of the information regarding this proposal, the commission finds and concludes that it should amend and adopt the rules as proposed in the CR-102 at WSR 08-07-080.
13 STATEMENT OF ACTION; STATEMENT OF EFFECTIVE DATE: After reviewing the entire record, the commission determines that chapter 480-75 WAC should be amended to read as set forth in Appendix A, as rules of the Washington utilities and transportation commission, to take effect pursuant to RCW 34.05.380(2) on the thirty-first day after filing with the code reviser.
Number of Sections Adopted in Order to Comply with Federal Statute: New 0, Amended 0, Repealed 0; Federal Rules or Standards: New 0, Amended 2, Repealed 0; or Recently Enacted State Statutes: New 0, Amended 35, Repealed 0.
Number of Sections Adopted at Request of a Nongovernmental Entity: New 0, Amended 0, Repealed 0.
Number of Sections Adopted on the Agency's Own Initiative: New 0, Amended 0, Repealed 0.
Number of Sections Adopted in Order to Clarify, Streamline, or Reform Agency Procedures: New 0, Amended 1, Repealed 0.
Number of Sections Adopted Using Negotiated Rule Making: New 0, Amended 0, Repealed 0; Pilot Rule Making: New 0, Amended 0, Repealed 0; or Other Alternative Rule Making: New 0, Amended 0, Repealed 0.
15 The commission amends chapter 480-75 WAC to read as set forth in Appendix A, as rules of the Washington utilities and transportation commission, to take effect on the thirty-first day after the date of filing with the code reviser pursuant to RCW 34.05.380(2).
16 This order and the rules set out below, after being recorded in the register of the Washington utilities and transportation commission, shall be forwarded to the code reviser for filing pursuant to chapters 80.01 and 34.05 RCW and 1-21 WAC.
DATED at Olympia, Washington, on May 29, 2008.
Washington State Utilities and Transportation Commission
Mark H. Sidran, Chairman
Patrick J. Oshie, Commissioner
Philip B. Jones, Commissioner
OTS-1365.3
HAZARDOUS LIQUID((, GAS, OIL AND PETROLEUM)) PIPELINES
((COMPANIES)) -- SAFETY
"Bedding" means the material placed in the bottom of a trench prior to laying a pipe.
"Breakout tank" means a tank that is used to relieve surges in a hazardous liquid pipeline system, or a tank used to receive and store hazardous liquid transported by a pipeline for reinjection and continued transportation by pipeline.
(("Company," "pipeline company," or "hazardous liquid
pipeline company" means a person or entity constructing,
owning, or operating a pipeline for transporting hazardous
liquid or carbon dioxide. A "pipeline company" does not
include: (a) Distribution systems owned and operated under
franchise for the sale, delivery, or distribution of natural
gas at retail; or (b) excavation contractors or other
contractors that contract with a pipeline company.))
"Hazardous liquid" means (a) petroleum, petroleum products, or anhydrous ammonia as those terms are defined in 49 CFR Part 195 and (b) carbon dioxide.
"Hazardous liquid pipeline" or "pipeline" means all parts of a pipeline facility through which hazardous liquid moves in transportation, including, but not limited to, line pipe, valves, and other appurtenances connected to line pipe, pumping units, fabricated assemblies associated with pumping units, metering and delivery stations and fabricated assemblies therein, and breakout tanks. It does not include all parts of a pipeline facility through which a hazardous liquid moves in transportation through refining or manufacturing facilities or storage or in-plant piping systems associated with such facilities, a pipeline subject to safety regulations of the United States Coast Guard, or a pipeline that serves refining, manufacturing, or truck, rail or vessel terminal facilities, if the pipeline is less than one mile long, measured outside facility grounds, and does not cross an offshore area or a waterway used for commercial navigation.
"Hazardous liquid pipeline company" or "pipeline company" means a person or entity constructing, owning, or operating a hazardous liquid pipeline, but does not include excavation contractors or other contractors that contract with a hazardous liquid pipeline company.
"Independent level alarm" means an alarm function actuated by a primary level sensing device that is separate and independent from any tank gauging equipment on the tank.
"Line pipe" or "pipe" means a tube, usually cylindrical, through which a hazardous liquid is transported from one point to another.
"Major construction" means any change in pipeline routing, either horizontally or depth, or replacement of existing pipe of one hundred feet or more in length.
"Maximum operating pressure (MOP)" means the maximum operating pressure at which a pipeline may be operated under 49 CFR Part 195.
"New pipeline" means a new hazardous liquid pipeline that
did not previously exist, or an extension of an existing
pipeline ((for)) of one hundred feet or longer.
(("Operator" means a person who owns or operates pipeline
facilities.))
"Person" means an individual, partnership, franchise holder, association, corporation, a state, a city, a county, or any political subdivision or instrumentality of a state, and its employees, agents, or legal representatives.
(("Pipeline," "pipeline system," or "hazardous liquid
pipeline" means all parts of a pipeline facility through which
hazardous liquid moves in transportation, including, but not
limited to, line pipe, valves, and other appurtenances
connected to line pipe, pumping units, fabricated assemblies
associated with pumping units, metering and delivery stations
and fabricated assemblies therein, and breakout tanks.
Pipeline or pipeline system does not include process or
transfer pipelines.
"Pipeline facility" means new and existing pipeline, rights of way and any equipment, facility, or building used in the transportation of hazardous liquids or carbon dioxide.))
"Release" means when hazardous liquid escapes from the pipeline.
"Subsoiling" means the agricultural practice of breaking compact subsoil.
"Telephonic notification" means verbal notification by telephone to the Washington utilities and transportation commission, pipeline safety division using the pipeline safety incident notification telephone number (1-888-321-9146).
[Statutory Authority: RCW 80.01.040 and 80.04.160. 02-18-032 (Docket No. TO-000712, General Order No. R-500), § 480-75-100, filed 8/26/02, effective 9/26/02.]
(2) While the commission's hazardous liquid pipeline safety statutes and rules impose obligations on pipeline companies, a pipeline company may contract with a person to do tasks that are subject to these rules, such as excavation, construction, and maintenance. If the pipeline company's contractor (or any of its subcontractors) engages in conduct that violates commission rules applicable to the pipeline company, the pipeline company is subject to penalties and all other applicable remedies, as if the pipeline company itself engaged in that conduct, including intentional noncompliance or other intentional violations of these rules by the contractor (or any of its subcontractors). The pipeline company is responsible for maintaining measures designed to detect intentional violations of these rules by a contractor and any of its subcontractors.
[Statutory Authority: RCW 80.01.040 and 80.04.160. 02-18-032 (Docket No. TO-000712, General Order No. R-500), § 480-75-200, filed 8/26/02, effective 9/26/02.]
(2) The commission retains the authority to impose additional or different requirements on any company in appropriate circumstances, consistent with the requirements of law.
[Statutory Authority: RCW 80.01.040 and 80.04.160. 02-18-032 (Docket No. TO-000712, General Order No. R-500), § 480-75-210, filed 8/26/02, effective 9/26/02.]
(2) Each company will pay an annual pipeline safety fee
as established in the methodology set forth in ((section (2)
below)) subsection (3) of this section.
(((2))) (3) The fee will be set by general order of the
commission entered before ((July)) September 1 of each year
and will be collected in four equal installments payable on
the first day of each ((calendar)) quarter as listed below:
1st quarter fee installment due September 1;
2nd quarter fee installment due December 1;
3rd quarter fee installment due March 1;
4th quarter fee installment due June 1.
(a) The total of pipeline safety fees will be calculated
to recover no more than the costs of the legislatively
authorized workload represented by current appropriations for
the commission's pipeline safety program, less the amount
received in total base grants through the Federal Department
of Transportation and less any amount received from penalties
collected under RCW 19.122.050. Federal grants, other than
the federal base grant, received by the commission for
additional activities not included or anticipated in the
legislatively directed workload will not be credited against
pipeline company ((pipeline)) safety fees, nor will the work
supported by ((such)) grants be considered a cost for purposes
of calculating ((such)) fees. To the extent that the actual
base grant proceeds are different than the amount credited,
the difference will be applied in the following year.
(b) Total pipeline safety fees as determined in (a) of this subsection will be calculated in two parts:
(i) The commission's annual overhead charge to the
pipeline safety program will be allocated among companies
according to each company's share of the total of all pipeline
miles within Washington as reported by ((the)) companies in
their annual reports to the commission.
(ii) After deducting the commission's annual overhead
charge, the remainder of the total pipeline safety fees will
be allocated among companies in proportion to each company's
share of the commission pipeline safety program staff hours
that are directly attributable to particular companies. The
commission will determine each company's share by dividing the
total hours directly attributable to ((the)) each company
during the two preceding calendar years (as reflected in the
program's timekeeping system) by the total of directly
attributable hours for all companies over the same period.
(iii) For fee-setting purposes, any program hours related
to a ((staff)) commission investigation of an incident found
to be attributed to third-party damage ((resulting)) that
results in penalties collected under RCW 19.122.055 will not
be directly attributed to the ((operator)) owner of the
damaged pipeline ((for fee-setting purposes)).
(c) The commission general order setting fees pursuant to this rule will detail the specific calculation of each company's pipeline safety fee including the allocations set forth in (b) of this subsection.
(((3))) (4) By ((June)) August 1 of each year the
commission ((staff)) will mail an invoice to each company ((an
invoice)).
(((4))) (5) All funds received by the commission for the
pipeline safety program will be deposited to the pipeline
safety account. For ((those companies)) each gas pipeline
company subject to RCW 81.24.010 ((the)), its portion of the
company's total regulatory fee applicable to pipeline safety
will be transferred from the public service revolving fund to
the pipeline safety account.
(((5))) (6) Any company wishing to contest the amount of
the fee imposed under this section must pay the fee when due
and, within ((6)) six months ((of)) after the due date of the
fee, file a written petition ((in writing)) with the
commission requesting a refund. The petition shall state the
name of the petitioner; the date and the amount paid,
including a copy of any receipt, if available; the amount of
the fee that is contested; ((and any)) all reasons why the
commission ((may)) should not impose the fee in that amount;
and a calculation and explanation of the fee amount the
petitioner contends is appropriate, if any. The commission
may grant the petition administratively or may set the
petition for adjudication ((or for brief adjudication)).
[Statutory Authority: RCW 80.01.040, 80.04.160, 81.04.160, 80.24.060, and 81.24.090. 05-17-017 (Docket No. P-041344, General Order No. R-523), § 480-75-240, filed 8/4/05, effective 7/1/06. Statutory Authority: RCW 80.01.040, 80.04.160, 81.04.160 and 2001 c 238 § 2. 02-03-016 (Docket No. UG-010522, General Order No. R-497), § 480-75-240, filed 1/4/02, effective 2/4/02.]
(2) In determining the amount of the penalty, the commission will consider the appropriateness of the penalty in relation to the position of the person charged with the violation.))
[Statutory Authority: RCW 80.01.040 and 80.04.160. 02-18-032 (Docket No. TO-000712, General Order No. R-500), § 480-75-250, filed 8/26/02, effective 9/26/02.]
(2) To request a rule exemption, a person must file with the commission a written request identifying the rule for which an exemption is sought, giving a full explanation of the reason for the exemption.
(3) The commission will assign the request a docket number, if it does not arise in an existing docket, and will schedule the request for consideration at one of its regularly scheduled open meetings or, if appropriate under chapter 34.05 RCW, in an adjudication. The commission will notify the person requesting the exemption, and other interested persons, of the date of the hearing or open meeting when the commission will consider the request.
(4) In determining whether to grant the request, the commission may consider whether application of the rule would impose undue hardship on the petitioner, of a degree or a kind different from hardship imposed on other similarly situated persons, and whether the effect of applying the rule would be contrary to the purpose of the rule.
(5) The commission will enter an order granting or denying the request, or setting it for hearing pursuant to chapter 480-07 WAC)) pursuant to WAC 480-07-110. Please refer to that rule for applicable procedures.
[Statutory Authority: RCW 80.01.040 and 80.04.160. 03-24-028 (General Order R-510, Docket No. A-010648), § 480-75-260, filed 11/24/03, effective 1/1/04; 02-18-032 (Docket No. TO-000712, General Order No. R-500), § 480-75-260, filed 8/26/02, effective 9/26/02.]
[Statutory Authority: RCW 80.01.040, 81.01.010, 81.88.060. 07-09-001 (Docket PL-061026, General Order R-541), § 480-75-270, filed 4/4/07, effective 5/5/07.]
(2) Leak detection systems must be capable of detecting an eight percent of maximum flow leak within fifteen minutes or less.
(3) Pipeline companies must have a leak detection
procedure and a procedure for responding to alarms. The
((operator)) pipeline company must maintain leak detection
maintenance and alarm records.
[Statutory Authority: RCW 80.01.040, 81.01.010, 81.88.060. 07-09-001 (Docket PL-061026, General Order R-541), § 480-75-300, filed 4/4/07, effective 5/5/07. Statutory Authority: RCW 80.01.040 and 80.04.160. 02-18-032 (Docket No. TO-000712, General Order No. R-500), § 480-75-300, filed 8/26/02, effective 9/26/02.]
[Statutory Authority: RCW 80.01.040 and 80.04.160. 02-18-032 (Docket No. TO-000712, General Order No. R-500), § 480-75-310, filed 8/26/02, effective 9/26/02.]
[Statutory Authority: RCW 80.01.040 and 80.04.160. 02-18-032 (Docket No. TO-000712, General Order No. R-500), § 480-75-320, filed 8/26/02, effective 9/26/02.]
[Statutory Authority: RCW 80.01.040 and 80.04.160. 02-18-032 (Docket No. TO-000712, General Order No. R-500), § 480-75-330, filed 8/26/02, effective 9/26/02.]
[Statutory Authority: RCW 80.01.040 and 80.04.160. 02-18-032 (Docket No. TO-000712, General Order No. R-500), § 480-75-340, filed 8/26/02, effective 9/26/02.]
[Statutory Authority: RCW 80.01.040 and 80.04.160. 02-18-032 (Docket No. TO-000712, General Order No. R-500), § 480-75-350, filed 8/26/02, effective 9/26/02.]
(a) A "class location unit" is an onshore area that
extends 220 yards (200 meters) on either side of the
centerline of any continuous ((1)) one mile (1.6 kilometers)
of pipeline.
(b) Each separate dwelling unit in a multiple dwelling unit building is counted as a separate building intended for human occupancy.
(2) Except as provided in subsection (3) of this section, pipeline locations are classified as follows:
(a) A Class 1 location is:
(i) An offshore area; or
(ii) Any class location unit that has ten or fewer buildings intended for human occupancy.
(b) A Class 2 location is any class location unit that has more than ten but fewer than forty-six buildings intended for human occupancy.
(c) A Class 3 location is:
(i) Any class location unit that has forty-six or more buildings intended for human occupancy; or
(ii) An area where the pipeline lies within 100 yards (91 meters) of either a building or a small, well-defined outside area (such as a playground, recreation area, outdoor theater, or other place of public assembly) that is occupied by twenty or more persons on at least five days a week for ten weeks in any twelve-month period. (The days and weeks need not be consecutive.)
(d) A Class 4 location is any class location unit where buildings with four or more stories above ground are prevalent.
(3) The pipeline company must adjust the continuous
one-mile of pipeline ((must be adjusted to include))
referenced in subsection (1)(a) of this section by including
all buildings in the higher class location. The class
location unit must encompass the highest classification of
buildings.
[Statutory Authority: RCW 80.01.040 and 80.04.160. 02-18-032 (Docket No. TO-000712, General Order No. R-500), § 480-75-360, filed 8/26/02, effective 9/26/02.]
Class location | Design factor (F) |
1 | 0.72 |
2 | 0.60 |
3 | 0.50 |
4 | 0.40 |
(a) Crosses the right of way of an unimproved public road, without a casing;
(b) Crosses without a casing, or makes a parallel encroachment on the right of way of either a hard-surfaced road, a highway, a public street, or a railroad;
(c) Is supported by a vehicular, pedestrian, railroad, or pipeline bridge; or
(d) Is used in a fabricated assembly (including mainline valve assemblies, cross-connections, and river crossing headers).
(2) For Class 2 locations, a design factor of 0.50, or less, must be used in the design formula in 49 CFR Section 195.106 for uncased steel pipe that crosses the right of way of a hard-surfaced road, a highway, a public street, or a railroad.
(3) For Class 1 and Class 2 locations, a design factor of 0.50, or less, must be used in the design formula in 49 CFR Section 195.106 for:
(a) Steel pipe in a pump station; and
(b) Steel pipe (including a pipe riser, on a platform located offshore or in inland navigable waters).
[Statutory Authority: RCW 80.01.040 and 80.04.160. 02-18-032 (Docket No. TO-000712, General Order No. R-500), § 480-75-370, filed 8/26/02, effective 9/26/02.]
[Statutory Authority: RCW 80.01.040 and 80.04.160. 02-18-032 (Docket No. TO-000712, General Order No. R-500), § 480-75-380, filed 8/26/02, effective 9/26/02.]
(2) When determining the type of valve to be used, its
location, and its shut-off time, ((a)) each pipeline company
must consider the following:
(a) Terrain;
(b) Geohazards;
(c) Drainage; and
(d) Type and condition of the pipe.
(3) Whenever a pipeline company installs a new rapid
shutdown valve ((is to be installed)), the pipeline company
must conduct a surge analysis to ensure that the surge
pressure in the pipeline will not exceed one hundred ten
percent of the maximum operating pressure as a result of a
rapid valve closure.
[Statutory Authority: RCW 80.01.040 and 80.04.160. 03-01-064 (Docket No. TO-000712, General Order No. R-508), § 480-75-390, filed 12/12/02, effective 1/12/03.]
(2) ((Where)) If the backfill material contains rocks or
hard lumps that could damage the pipeline coating, the
pipeline company must take care ((must be taken)) to protect
the pipe and the pipe coating from damage ((by such means as
the use of)), such as using mechanical shield material.
(3) ((Backfilling procedures)) A pipeline company's
backfill practices must not cause distortion of the pipe
cross-section that would be detrimental to the operation of
the piping, or the passage of cleaning devices, ((or))
internal inspection devices, or other similar devices.
(4) ((Backfilling must be performed)) A pipeline company
must apply backfill material in such a manner as to prevent
excessive subsidence or erosion of the backfill and support
material. Where a ditch is flooded, ((care must be exercised
so)) the pipeline company must assure that the pipe is not
floated from the bottom of the ditch prior to completing the
backfill ((completion)).
(5) For open trench installations that cross paved areas
subject to vehicular loading, the ((backfill must be
compacted)) pipeline company must compact the backfill in
layers to a minimum of ninety-five percent relative density.
(6) The bedding and backfill material a pipeline company
uses must ((be)) consist of clean sand or soil and it must not
contain any stones ((having a maximum dimension)) larger than
one-half inch. ((Material must be placed to)) The pipeline
company must place the bedding and backfill material at a
minimum depth of six inches under the pipe and six inches over
the top of the pipe. The remaining backfill must not contain
rock larger than six inches. The pipeline company shall not
use organic material ((and)) or wood ((is not permitted)) for
bedding ((and)) or backfill.
[Statutory Authority: RCW 80.01.040 and 80.04.160. 02-18-032 (Docket No. TO-000712, General Order No. R-500), § 480-75-400, filed 8/26/02, effective 9/26/02.]
[Statutory Authority: RCW 80.01.040 and 80.04.160. 02-18-032 (Docket No. TO-000712, General Order No. R-500), § 480-75-410, filed 8/26/02, effective 9/26/02.]
(1) ((When)) If a pipeline company uses a manifold ((is
used)) for hydrostatic testing, ((then)) the company must
provide an isolation valve ((must be provided)) between the
pressure testing manifold and the pipeline being tested. The
isolation valve must be rated for the manifold test pressure
when in the closed position. The pipeline company must
separately pressure ((testing)) test the manifold used in the
actual pressure test ((must be separately pressure tested)) to
at least 1.2 times the pipeline test pressure, but not less
than the discharge pressure of the pump used for the pressure
testing.
(2) ((When)) If a pipeline company uses a pressure relief
valve ((is used)) to protect the pipe, ((then the pressure
relief)) each such valve(((s))) must be of adequate capacity
and set to relieve at ten percent above the hydrostatic test
pressure. The ((relief valves)) pipeline company must ((be
calibrated)) calibrate the relief valve within one month prior
to the ((hydrotest)) hydrostatic test.
(3) The pipeline company may use a bleed valve ((may be
provided)) to protect the pipeline from overpressure. When a
pipeline company uses a bleed valve ((is used, it)), the valve
must be readily accessible in case immediate depressurization
is required.
(4) ((A test chart or other recording method that shows
that the pressure was maintained at the minimum test pressure
throughout the entire test must be documented for all
hydrostatic tests. A company representative must sign and
date the test to certify the validity of the test. All
equipment such as hoses, piping, and other equipment used to
hydrostatically test the pipe must be rated for at least the
target pressure. Each hydrostatic test of a pipeline must be
documented to show:)) All equipment such as hoses, piping, and
other equipment used to hydrostatically test the pipe must be
rated for at least the target pressure.
(5) The pipeline company must maintain documents identifying how each hydrostatic test was conducted. Each document must be signed by a person with sufficient knowledge, certifying that the document contains accurate information about the test. The documents must contain the following information:
(a) The date of the test ((date));
(b) ((Signature of the certifying agent;)) A test chart
or other record that shows that the pressure was maintained at
the minimum test pressure throughout the entire test;
(c) Beginning and ending times of the test;
(d) Beginning and ending temperatures; and
(e) Highest and lowest pressure achieved.
(((5))) (6) The pipeline company must conspicuously post
precautions such as warning signs ((must be posted))
indicating that a hazardous liquid pipeline is under test
conditions.
(((6) Companies)) (7) The pipeline company must notify
((public officials who have)) the local government and fire
department with jurisdiction ((encompassing)) in the area
affected by the ((pipeline)) hydrostatic test.
(((7) No additional)) (8) The pipeline company shall not
add any water ((is allowed to be added)) to the pipeline
((once)) after the hydrostatic test has started. ((As))
Because pressure varies significantly with changing test water
temperatures, each ((operator)) pipeline company must take
into consideration temperature variations in the test water
before accepting the test results.
(((8) Before conducting a hydrostatic test, a)) (9) The
pipeline company ((needs to consider)) must comply with
applicable rules of the Washington state department of ecology
((regulations for)) addressing disposal of testing water.
[Statutory Authority: RCW 80.01.040 and 80.04.160. 02-18-032 (Docket No. TO-000712, General Order No. R-500), § 480-75-420, filed 8/26/02, effective 9/26/02.]
(a) ((Operators)) To qualify or requalify a welder or to
qualify a welding procedure, each pipeline company must use
testing equipment ((necessary to measure)) capable of
measuring the essential variables used during ((welder
qualification or requalification, and also for procedure
qualification or requalification.)) the test. Each pipeline
company must record all essential variables ((must be recorded
as)) performed during the ((welding)) qualification or
requalification.
(b) Each pipeline company must have the appropriate
written qualified welding procedures ((must be on-site)) at
the site where the welding is being performed.
(2) Each welder((s)) used by a pipeline company must
carry appropriate identification and qualification cards
showing the name of welder, ((their)) qualifications, the date
((of)) qualification ((expiration)) expires, and the name of
the pipeline company whose procedures ((were followed)) the
welder used for the qualification. Each welder((s'))'s
identification and qualification card((s)) will be subject to
commission inspection at all times when ((personnel are)) a
welder is working on ((facilities)) a facility subject to the
commission's pipeline safety jurisdiction.
[Statutory Authority: RCW 80.01.040 and 80.04.160. 02-18-032 and 02-20-015 (Docket No. TO-000712, General Order No. R-500 and R-502), § 480-75-430, filed 8/26/02 and 9/20/02, effective 9/26/02 and 10/21/02.]
[Statutory Authority: RCW 80.01.040 and 80.04.160. 02-18-032 (Docket No. TO-000712, General Order No. R-500), § 480-75-440, filed 8/26/02, effective 9/26/02.]
[Statutory Authority: RCW 80.01.040, 81.01.010, 81.88.060. 07-09-001 (Docket PL-061026, General Order R-541), § 480-75-450, filed 4/4/07, effective 5/5/07. Statutory Authority: RCW 80.01.040 and 80.04.160. 02-18-032 (Docket No. TO-000712, General Order No. R-500), § 480-75-450, filed 8/26/02, effective 9/26/02.]
[Statutory Authority: RCW 80.01.040 and 80.04.160. 02-18-032 (Docket No. TO-000712, General Order No. R-500), § 480-75-460, filed 8/26/02, effective 9/26/02.]
[Statutory Authority: RCW 80.01.040 and 80.04.160. 02-18-032 (Docket No. TO-000712, General Order No. R-500), § 480-75-500, filed 8/26/02, effective 9/26/02.]
[Statutory Authority: RCW 80.01.040 and 80.04.160. 02-18-032 (Docket No. TO-000712, General Order No. R-500), § 480-75-510, filed 8/26/02, effective 9/26/02.]
[Statutory Authority: RCW 80.01.040 and 80.04.160. 02-18-032 (Docket No. TO-000712, General Order No. R-500), § 480-75-520, filed 8/26/02, effective 9/26/02.]
[Statutory Authority: RCW 80.01.040 and 80.04.160. 02-18-032 (Docket No. TO-000712, General Order No. R-500), § 480-75-530, filed 8/26/02, effective 9/26/02.]
[Statutory Authority: RCW 80.01.040 and 80.04.160. 02-18-032 (Docket No. TO-000712, General Order No. R-500), § 480-75-540, filed 8/26/02, effective 9/26/02.]
[Statutory Authority: RCW 80.01.040 and 80.04.160. 02-18-032 (Docket No. TO-000712, General Order No. R-500), § 480-75-550, filed 8/26/02, effective 9/26/02.]
(2) Each pipeline company must make books, records, reports, and other information available to the commission, so the commission or its authorized representatives can determine whether pipeline the company is in compliance with state and federal regulations.
(3) ((When pipeline facilities are modified,)) The
pipeline company shall assure that all construction records,
((revision to)) maps, and operating history documents are
current and made available to appropriate pipeline operations
personnel ((must be updated within six months)).
[Statutory Authority: RCW 80.01.040 and 80.04.160. 02-18-032 (Docket No. TO-000712, General Order No. R-500), § 480-75-600, filed 8/26/02, effective 9/26/02.]
(a) Description and purpose of the proposed ((pipeline))
construction;
(b) Pipe specifications and route map;
(c) Maximum operating pressure for which the pipeline is being constructed;
(d) Location and construction details of all river crossings or other unusual construction requirements encountered en route; i.e., places where pipe will be exposed or it is impractical to provide required cover, bridge crossings, lines to be laid parallel to railroads or state highways and encroachments, and other areas requiring special or unusual design and construction considerations;
(e) Corrosion control plan that includes the specifications for coating and for wrapping;
(f) Welding specifications and welding inspection methods and procedures required during construction of the pipeline;
(g) Required bending procedures; and
(h) Location and specification of all mainline block valves indicating whether the valves will be operated by manual or remote control. Indicate other auxiliary equipment to be installed as a part of the pipeline system to be constructed.
(2) For pipelines operating under twenty percent
specified minimum yield strength, ((companies)) a pipeline
company must submit to the commission a written notice at
least forty-five days prior to the proposed construction. The
notice must include a project description and timeline.
(3) The commission may waive the forty-five-day reporting requirement in an emergency.
[Statutory Authority: RCW 80.01.040 and 80.04.160. 02-18-032 (Docket No. TO-000712, General Order No. R-500), § 480-75-610, filed 8/26/02, effective 9/26/02.]
[Statutory Authority: RCW 80.01.040 and 80.04.160. 02-18-032 (Docket No. TO-000712, General Order No. R-500), § 480-75-620, filed 8/26/02, effective 9/26/02.]
(a) A fatality;
(b) Personal injury requiring hospitalization;
(c) Fire or explosion not intentionally set by the
((operator)) pipeline company;
(d) Spills of five gallons or more of product from the pipeline;
(e) Damage to the property of the pipeline company and others of a combined total cost exceeding twenty-five thousand dollars (automobile collisions and other equipment accidents not involving hazardous liquid or hazardous-liquid-handling equipment need not be reported under this rule);
(f) A significant occurrence in the judgment of the pipeline company, even though it does not meet the criteria of (a) through (e) of this subsection;
(g) The news media reports the occurrence, even though it does not meet the criteria of (a) through (f) of this subsection.
(2) Each pipeline company that has an incident described
in subsection (1) of this section shall send a written report
((must be sent)) to the commission within ((one month)) thirty
calendar days of the incident. The report must include the
following:
(a) Name(s) and address(es) of any person or persons injured or killed or whose property was damaged;
(b) The extent of injuries and damage;
(c) A description of the incident including date, time, and place;
(d) A description and maximum operating pressure of the
((hazardous liquid facilities)) pipeline implicated in the
incident and the system operating pressure at the time of the
incident;
(e) The date and time the ((hazardous liquid facility))
pipeline returns to safe operations; and
(f) The date, time, and type of any temporary or permanent repair.
(3) ((An operator)) A pipeline company must give the
commission telephonic notification within twenty-four hours of
emergency situations including emergency shutdowns, material
defects, or physical damage that impairs the serviceability of
the pipeline.
[Statutory Authority: RCW 80.01.040, 81.01.010, 81.88.060. 07-09-001 (Docket PL-061026, General Order R-541), § 480-75-630, filed 4/4/07, effective 5/5/07. Statutory Authority: RCW 80.01.040 and 80.04.160. 02-18-032 (Docket No. TO-000712, General Order No. R-500), § 480-75-630, filed 8/26/02, effective 9/26/02.]
(1) Unless specifically exempted in this section, each
pipeline company must bury all pipe ((must be buried)) so that
it is below the level of cultivation. Except as provided in
subsection (2) of this section, the pipe must be installed so
that the cover between the top of the pipe and the ground
level, road bed, river bottom, or sea bottom, as applicable,
complies with the following table:
Location | Cover
(inches) For normal excavation |
Cover (inches) For rock excavation |
Industrial, commercial, and residential areas | 36 | 30 |
Crossings of inland
bodies of water with a width of at least 100 ft. from high water mark to high water mark |
48 | 18 |
Drainage ditches at public roads and railroads | 36 | 36 |
Deepwater port safety zone | 48 | 24 |
Any other area | 30 | 18 |
Note: | Rock excavation is any excavation that requires blasting or removal by equivalent means. |
(a) It is impracticable for the pipeline company to comply with the minimum cover requirements; and
(b) The pipeline company provides additional protection
((is provided that is)) equivalent to the minimum required
cover.
[Statutory Authority: RCW 80.01.040 and 80.04.160. 02-18-032 (Docket No. TO-000712, General Order No. R-500), § 480-75-640, filed 8/26/02, effective 9/26/02.]
(1) A copy of Pipeline and Hazardous Materials Safety Administration (PHMSA) F-7000.1-1 annual report required by the PHMSA, Office of Pipeline Safety.
(2) A report titled, "Hazardous Liquid Annual Report Form" which can be obtained from the Pipeline Safety Section of the commission. The annual report must include in detail the following information:
(a) Interstate and intrastate pipeline mileage in Washington state; and
(b) A list of reportable and nonreportable safety-related conditions as defined in 49 CFR Section 195.55.
[Statutory Authority: RCW 80.01.040, 81.01.010, 81.88.060. 07-09-001 (Docket PL-061026, General Order R-541), § 480-75-650, filed 4/4/07, effective 5/5/07. Statutory Authority: RCW 80.01.040 and 80.04.160. 02-18-032 (Docket No. TO-000712, General Order No. R-500), § 480-75-650, filed 8/26/02, effective 9/26/02.]
(2) A log sheet must be included in the plan to record amendments. The log sheet must include the date the old section was eliminated, any new sections that were added, the date, the initials of the individual making the change, and the signature of the person responsible for reviewing the amendment. A description of the amendment(s) and its purpose must be included.
(a) At a minimum, the plan must include the following:
(i) The requirements in chapter 480-75 WAC;
(ii) A schedule of inspection and testing of all the mechanical components and electronic components within the pipeline system;
(iii) Structural integrity of all pipelines determined through pressure testing, in-line inspection surveys, or other appropriate techniques;
(iv) Failsafe systems including emergency shutdown and isolation procedures;
(v) Emergency management training for operators;
(vi))) and follow a procedural manual that includes the following:
(a) Procedures required in 49 CFR Section 195.402;
(b) Procedures for responding to earthquakes ((that must
include)), including a threshold for line shutoff, and
procedures for integrity monitoring prior to restart; and
(((vii))) (c) Procedure for assessing the potential for
impacts on the pipeline system due to landslides. ((Operators)) Pipeline companies with facilities located
within potential landslide areas must develop monitoring and
remediation procedures for ensuring that pipeline integrity is
maintained in these areas.
(((3) Companies must submit a plan to the commission
within twelve months after the adoption of this rule. New
companies must submit a plan to the commission no later than
sixty days prior to startup.
The plan must be submitted to:
Washington Utilities and Transportation Commission
Pipeline Safety Division
P.O. Box 47250
1300 S. Evergreen Park Dr. SW
Olympia, WA 98504-7250
(4) Amendments to the plan must be submitted to the commission within thirty days of the change.
(5) Companies must ensure that appropriate personnel are trained and familiar with the plan's content.)) (2) Each pipeline company shall submit a copy of its current procedural manual to the commission and must submit any revisions to the procedural manual to the commission within thirty days of the procedural manual change. A new pipeline company must submit its procedural manual no later than sixty days prior to startup.
[Statutory Authority: RCW 80.01.040 and 80.04.160. 02-18-032 (Docket No. TO-000712, General Order No. R-500), § 480-75-660, filed 8/26/02, effective 9/26/02.]
(1) Title 49 Code of Federal Regulations, cited as 49
CFR, Parts 195 and 199 including all appendices and amendments
except for 49 CFR Sections 195.0((,)) and 195.1, and 49 CFR
Sections 199.1 and 199.2, published by the United States
Government Printing Office.
(a) The commission adopts the version in effect on
October 1, ((2005)) 2007.
(b) This publication is referenced in WAC 480-75-370 (Design factor (F) for steel pipe), WAC 480-75-630 (Incident reporting), and WAC 480-75-660 (Operations safety plan requirements).
(c) Copies of Title 49 Code of Federal Regulations are available from the U.S. Government Online Bookstore, http://bookstore.gpo.gov/, and from various third-party vendors.
(2) The American Society of Mechanical Engineers (ASME) B31.4, 1998 edition.
(a) This publication is referenced in WAC 480-75-350 (Design specifications for new pipeline projects), WAC 480-75-440 (Pipeline repairs), and WAC 480-75-450 (Construction specifications).
(b) Copies of ASME B31.4 are available from The American Society of Mechanical Engineers, Park Avenue New York, New York.
(3) The 2001 edition of Section IX of the ASME Boiler and Pressure Vessel Code.
(a) This publication is referenced in WAC 480-75-430 (Welding procedures).
(b) Copies of Section IX of the ASME Boiler and Pressure Vessel Code are available from The American Society of Mechanical Engineers, Park Avenue, New York, New York.
(4) The commission adopts American Petroleum Institute (API) standard 1104 19th edition.
(a) This publication is referenced in WAC 480-75-430 (Welding procedures) and WAC 480-75-460 (Welding inspection requirements).
(b) Copies of API standard 1104 19th edition are available from the Office of API Publishing Services in Washington DC.
(5) The commission adopts API RP standard 1117 Second Edition, August 1996.
(a) This publication is referenced in WAC 480-75-500 (Moving and lowering hazardous liquid pipelines).
(b) Copies of API standard 1117 Second Edition are available from Global Engineering Documents in Englewood, Colorado.
[Statutory Authority: RCW 80.01.040, 80.04.160, 80.28.210, 81.04.160, 81.88.020, and 34.05.353. 06-14-052 (Docket A-060464, General Order No. R-535), § 480-75-999, filed 6/28/06, effective 7/29/06. Statutory Authority: RCW 80.01.040, 80.04.160, 81.04.160 and 34.05.353. 05-21-022 (Docket No. A-050271, General Order No. R-521), § 480-75-999, filed 10/10/05, effective 11/10/05; 04-01-152 (General Order No. R-511, Docket No. A-030852), § 480-75-999, filed 12/22/03, effective 1/22/04. Statutory Authority: RCW 80.01.040 and 80.04.160. 02-18-032 (Docket No. TO-000712, General Order No. R-500), § 480-75-999, filed 8/26/02, 9/26/02. Statutory Authority: RCW 80.01.040, 80.04.160, 81.04.160, and 34.05.310. 01-20-061 (Docket No. A-010827, General Order No. R-491), § 480-75-999, filed 9/28/01, effective 10/29/01.]