WSR 02-11-008

PERMANENT RULES

COUNTY ROAD

ADMINISTRATION BOARD

[ Filed May 2, 2002, 1:45 p.m. ]

     Date of Adoption: April 18, 2002.

     Purpose: Amends WAC 136-130-030 Project prioritization in the Puget Sound region and 136-130-070 Project prioritization in the southwest region.

     Citation of Existing Rules Affected by this Order: Amending Title 136 WAC.

     Statutory Authority for Adoption: Chapter 36.79 RCW.

      Adopted under notice filed as WSR 02-06-105 on March 5, 2002.

     Number of Sections Adopted in Order to Comply with Federal Statute: New 0, Amended 0, Repealed 0; Federal Rules or Standards: New 0, Amended 0, Repealed 0; or Recently Enacted State Statutes: New 0, Amended 0, Repealed 0.

     Number of Sections Adopted at Request of a Nongovernmental Entity: New 0, Amended 0, Repealed 0.

     Number of Sections Adopted on the Agency's Own Initiative: New 0, Amended 0, Repealed 0.

     Number of Sections Adopted in Order to Clarify, Streamline, or Reform Agency Procedures: New 0, Amended 0, Repealed 0.

     Number of Sections Adopted Using Negotiated Rule Making: New 0, Amended 0, Repealed 0;      Pilot Rule Making: New 0, Amended 0, Repealed 0; or Other Alternative Rule Making: New 0, Amended 0, Repealed 0.
     Effective Date of Rule: Thirty-one days after filing.

April 29, 2002

Jay P. Weber

Executive Director

OTS-5525.1


AMENDATORY SECTION(Amending WSR 01-05-009, filed 2/8/01, effective 3/11/01)

WAC 136-130-030   Project prioritization in Puget Sound region (PSR).   Each county in the PSR may submit projects requesting RATA funds not to exceed 80% of the forecasted regional apportionment. Each project shall be rated in accordance with the PSR RAP rating procedures. The PSR funding period shall allot a minimum of 25% of the forecasted regional apportionment to projects on roads classified as major collectors (07) or minor collectors (08). ((PSR RAP rating points shall be assigned on the basis of twenty points for traffic volume, twenty-five points for accident history, fifteen points for structural condition, twenty-five points for geometric condition, and fifteen points for special use and need.))

     PSR RAP maximum rating points for the three project types shall be assigned based on the following:

Project Type:
Rating Criteria: Road Intersection Bridge
Traffic Volume 20 20 20
Accident History 25 25 25
Structure 15 5 20
Geometry 25 35 20
Special Road Usage 15 15 15
TOTAL POINTS 100 100 100

     Bridge category projects that will not replace the structure must have federal funds committed to them prior to submittal for RATA funding.

     Prioritization of PSR projects shall be on the basis of total PSR RAP rating points shown on the project worksheet and the prospectus form of the project application.

[Statutory Authority: Chapter 36.79 RCW. 01-05-009, § 136-130-030, filed 2/8/01, effective 3/11/01; 99-01-021, § 136-130-030, filed 12/7/98, effective 1/7/99; 98-09-070, § 136-130-030, filed 4/20/98, effective 5/21/98. Statutory Authority: RCW 36.79.060. 92-13-038 (Order 88), § 136-130-030, filed 6/10/92, effective 7/11/92. Statutory Authority: RCW 36.79.060 and 1983 1st ex.s. c 49. 90-22-083 (Order 82), § 136-130-030, filed 11/6/90, effective 12/7/90. Statutory Authority: Chapter 36.78 RCW. 86-06-005 (Order 61), § 136-130-030, filed 2/20/86; 84-16-065 (Order 56), § 136-130-030, filed 7/30/84.]


AMENDATORY SECTION(Amending WSR 01-05-009, filed 2/8/01, effective 3/11/01)

WAC 136-130-070   Project prioritization in southwest region (SWR).   Each county in the SWR may submit projects requesting RATA funds not to exceed thirty percent of the forecasted SWR biennial apportionment. No bridge replacement projects will be funded. Each project shall be rated in accordance with the SWR RAP rating procedures. SWR RAP rating points shall be assigned on the basis of fifty road condition points, consisting of twenty-five points for structural condition and twenty-five points for surface condition, fifty points for geometrics, ten points for traffic volume and ten points for traffic accidents, except that portland cement concrete surfaces and asphalt surfaces with cement concrete bases shall have fifty points for road surface condition and no points for structural condition and except that gravel roads shall have ((thirty-five)) fifty points maximum for surface condition, and fifteen points maximum for roadbed width in geometrics and no other geometric points. Prioritization of SWR projects shall be on the basis of total SWR RAP rating points shown on the project worksheets and the prospectus form of the project application.

[Statutory Authority: Chapter 36.79 RCW. 01-05-009, § 136-130-070, filed 2/8/01, effective 3/11/01; 99-24-057, § 136-130-070, filed 11/29/99, effective 12/30/99; 99-01-021, § 136-130-070, filed 12/7/98, effective 1/7/99. Statutory Authority: RCW 36.79.060. 92-13-038 (Order 88), § 136-130-070, filed 6/10/92, effective 7/11/92. Statutory Authority: RCW 36.79.060 and 1983 1st ex.s. c 49. 90-22-083 (Order 82), § 136-130-070, filed 11/6/90, effective 12/7/90. Statutory Authority: Chapter 36.78 RCW. 88-05-040 (Order 68), § 136-130-070, filed 2/16/88; 86-06-005 (Order 61), § 136-130-070, filed 2/20/86; 84-16-065 (Order 56), § 136-130-070, filed 7/30/84.]