Title of Rule and Other Identifying Information: Chapter 296-45 WAC, Safety standards for electrical workers.
THIS RULE IS BEING PROPOSED UNDER AN EXPEDITED RULE-MAKING PROCESS THAT WILL ELIMINATE THE NEED FOR THE AGENCY TO HOLD PUBLIC HEARINGS, PREPARE A SMALL BUSINESS ECONOMIC IMPACT STATEMENT, OR PROVIDE RESPONSES TO THE CRITERIA FOR A SIGNIFICANT LEGISLATIVE RULE. IF YOU OBJECT TO THIS USE OF THE EXPEDITED RULE-MAKING PROCESS, YOU MUST EXPRESS YOUR OBJECTIONS IN WRITING AND THEY MUST BE SENT TO Carmen Moore, Rules Coordinator, Department of Labor and Industries, P.O. Box 44001, Olympia, WA 98504-4001 , AND RECEIVED BY May 24, 2005.
Purpose of the Proposal and Its Anticipated Effects, Including Any Changes in Existing Rules: The purpose of this proposal is to be at-least-as-effective-as the Occupational Safety and Health Administration (OSHA). The department received letters from OSHA indicating that we were not as-effective-as the federal requirements relating to the electrical standard, chapter 296-45 WAC. For example:
• | A qualified employee must position themselves so that he/she is neither within reach of nor otherwise exposed to contact with energized parts. |
• | The fall protection requirements relating to lineman's belts, safety straps and lanyards currently reference the employer to another standard, therefore we are incorporating them into chapter 296-45 WAC. |
WAC 296-45-25510 Fall protection.
• | Add a new subsection (2) relating to specific requirements about lineman's belts, safety straps, and lanyards. The language being proposed is the OSHA requirements and our proposed language is identical to OSHA. This is being done as a result of WISHA receiving a "not at-least-as-effective-as" letter from OSHA. |
• | Add a new paragraph (d) in subsection (4) relating to pole handling and framing operations. The language being proposed is OSHA requirements and our proposed language is identical to OSHA. This is being done as a result of WISHA receiving a "not at-least-as-effective-as" letter from OSHA. |
• | Add language in paragraph (3) relating to qualified employees positioning themselves so that he/she is neither within reach of nor otherwise exposed to contact with energized parts. This is being done as a result of WISHA receiving a "not at-least-as-effective-as" letter from OSHA. |
• | Revise language in subsection (2)(d) relating to installing and removing overhead lines. This is being done as a result of WISHA receiving a "not at-least-as-effective-as" letter from OSHA. |
• | Add a new subsection (2)(n) relating to each pull being snubbed or dead ended. The language being proposed is OSHA requirements and our proposed language is identical to OSHA. This is being done as a result of WISHA receiving a "not at-least-as-effective-as" letter from OSHA. |
• | Add a new subsection (13)(d) and (e) relating to towers and structures. The language being proposed is OSHA requirements and our proposed language is identical to OSHA. This is being done as a result of WISHA receiving a "not at-least-as-effective-as" letter from OSHA. |
• | Add a new subsection (14) relating to conductors, subconductors, and overhead ground conductors being bonded to a tower. The language being proposed is OSHA requirements and our proposed language is identical to OSHA. This is being done as a result of WISHA receiving a "not at-least-as-effective-as" letter from OSHA. |
• | Renumbered current subsections (14), (15) and (16) to subsections (15), (16) and (17) because of the new subsection (14) mentioned above. |
• | Add a new subsection (1)(d) relating to access and working space. The language being proposed is OSHA requirements and our proposed language is identical to OSHA. This is being done as a result of WISHA receiving a "not at-least-as-effective-as" letter from OSHA. |
• | Revise language in subsection (3) relating to substation fences. This is being done as a result of WISHA receiving a "not at-least-as-effective-as" letter from OSHA. |
Reasons Supporting Proposal: The department is updating the standard to be at-least-as-effective-as OSHA.
Statutory Authority for Adoption: RCW 49.17.010, 49.17.040, 49.17.050, 49.17.060.
Statute Being Implemented: Chapter 49.17 RCW.
Rule is not necessitated by federal law, federal or state court decision.
Name of Proponent: Department of Labor and Industries, governmental.
Name of Agency Personnel Responsible for Drafting: Tracy Spencer, Tumwater, (360) 902-5530; Implementation and Enforcement: Michael Wood, Tumwater, (360) 902-5495.
March 22, 2005
Judy Schurke
Acting Director
OTS-7873.1
AMENDATORY SECTION(Amending WSR 98-07-009, filed 3/6/98,
effective 5/6/98)
WAC 296-45-25510
Fall protection.
(1) Personal fall
arrest equipment shall meet the requirements of WAC 296-155-245.
(2) ((Body belts and safety straps for work positioning
shall meet the requirements of WAC 296-155-245.)) Specific
requirements for lineman's belts, safety straps and lanyards.
(a) All fabric used for safety straps must withstand an A.C. dielectric test of not less than 25,000 volts per foot "dry" for 3 minutes, without visible deterioration.
(b) All fabric and leather used must be tested for leakage current and must not exceed 1 milliampere when a potention of 3,000 volts is applied to the electrodes positioned 12 inches apart.
(c) Direct current tests may be permitted in lieu of alternating current tests.
(d) The cushion part of the body belt must:
(i) Contain no exposed rivets on the inside;
(ii) Be at least three (3) inches in width;
(iii) Be at least five thirty-seconds (5/32) inch thick, if made of leather; and
(iv) Have pocket tabs that extended at least 1 1/2 inches down and three (3) inches back of the inside of circle of each D ring for riveting on plier or tool pockets. On shifting D belts, this measurement for pocket tabs must be taken when the D ring section is centered.
(e) A maximum of four (4) tool loops must be so situated on the body belt that four (4) inches of the body belt in the center of the back, measuring from D ring to D ring, must be free of tool loops, and any other attachments.
(f) Suitable copper, steel, or equivalent liners must be used around bar of D rings to prevent wear between these members and the leather or fabric enclosing them.
(g) All stitching must be of a minimum 42-pound weight nylon or equivalent thread and must be lock stitched. Stitching parallel to an edge must not be less than three-sixteenths (3/16) inch from edge of narrowest member caught by the thread. The use of cross stitching on leather is prohibited.
(h) The keeper of snaphooks must have a spring tension that will not allow the keeper to begin to open with a weight of 2 1/2 pounds or less, but the keeper of snaphooks must begin to open with a weight of four (4) pounds, when the weight is supported on the keeper against the end of the nose.
(i) Testing of lineman's safety straps, body belts and lanyards must be in accordance with the following procedure:
(i) Attach one end of the safety strap or lanyard to a rigid support, the other end must be attached to a 250-pound canvas bag of sand;
(ii) Allow the 250-pound canvas bag of sand to free fall 4 feet for (safety strap test) and 6 feet for (lanyard test); in each case stopping the fall of the 250-pound bag;
(iii) Failure of the strap or lanyard must be indicated by any breakage, or slippage sufficient to permit the bag to fall free of the strap or lanyard. The entire "body belt assembly" must be tested using one D ring. A safety strap or lanyard must be used that is capable of passing the "impact loading test" and attached as required in (i)(i) of this subsection. The body belt must be secured to the 250-pound bag of sand at a point to simulate the waist of a man and allowed to drop as stated in (i)(ii) of this subsection. Failure of the body belt must be indicated by any breakage, or slippage sufficient to permit the bag to fall free of the body belt.
(3) Body belts, safety straps, lanyards, lifelines, and body harnesses shall be inspected before use each day to determine that the equipment is in safe working condition. Defective equipment may not be used.
(4) Employees shall not wear climbers while doing work where they are not required. Employees shall not continue to wear their climbers while working on the ground; except for momentary or short periods of time on the ground.
(5) Employees, when working from a hook ladder, must either belt themselves securely to the ladder, attach themselves to the structures by means of a safety line, or belt themselves to ladder safety equipment, which shall consist of a safety rope or belting threaded through the rungs or secured to the ladder at intervals of not more than three feet.
(6) Before an employee throws his/her weight on a belt, the employee shall determine that the snap or fasteners are properly engaged.
(7) Safety straps shall not be placed around poles above the cross-arm except where it is not possible for the strap to slide or be slipped over the top of the pole by inadvertence of the employee. Neither end of the strap shall be allowed to hang loose or dangle while the employee is ascending or descending poles or other structures.
(8) Body belts and safety straps shall not be stored with sharp-edged tools or near sharp objects. When a body belt, safety strap and climbers are kept in the same container, they shall be stored in such a manner as to avoid cutting or puncturing the material of the body belt or safety strap with the gaffs or climbers.
(9) Employees shall not attach metal hooks or other metal devices to body belts. Leather straps or rawhide thongs shall have hardwood or fibre crossbars. Leather straps and rawhide thongs shall not have metal or other conductive crossbars on them.
(10) Climbing gaffs shall be kept properly sharpened and shall be at least 1-1/8 inches in length.
(11) Lifelines shall be protected against being cut or abraded.
(12) Fall arrest equipment, work positioning equipment,
or travel restricting equipment shall be used by employees
working at elevated locations more than 4 feet (1.2 m) above
the ground on poles, towers, or similar structures if other
fall protection has not been provided. Fall protection
equipment is not required to be used by a qualified employee
climbing or changing location on poles, towers, or similar
structures, unless conditions, such as, but not limited to,
ice, high winds, the design of the structure (for example, no
provision for holding on with hands), or the presence of
contaminants on the structure, could cause the employee to
lose his or her grip or footing.
(a) When stopping or arresting a fall, personal fall
arrest systems shall limit the maximum arresting force on an
employee to 1800 pounds (8 kN) if used with a body harness. (b) Personal fall arrest systems shall be rigged such
that an employee can neither free fall more than 6 feet (1.8
m) nor contact any lower level. (14) If vertical lifelines or droplines are used, not
more than one employee may be attached to any one lifeline. (15) Snaphooks may not be connected to loops made in
webbing-type lanyards. (16) Snaphooks may not be connected to each other.
[Statutory Authority: RCW 49.17.010, [49.17].040, [49.17].050
and [49.17].060. 98-07-009, § 296-45-25510, filed 3/6/98,
effective 5/6/98.] (2) Materials storage near energized lines or equipment. In areas not restricted to qualified persons only, materials
or equipment may not be stored closer to energized lines or
exposed energized parts of equipment than the following
distances plus an amount providing for the maximum sag and
side swing of all conductors and providing for the height and
movement of material handling equipment: (a) For lines and equipment energized at 50 kV or less,
the distance is 10 feet (305 cm). (b) For lines and equipment energized at more than 50 kV,
the distance is 10 feet (305 cm) plus 4 inches (10 cm) for
every 10 kV over 50 kV. (c) In areas restricted to qualified employees, material
may not be stored within the working space about energized
lines or equipment. (4) Pole handling. (a) During pole hauling operations, all loads shall be
secured to prevent displacement, and a red flag shall be
displayed at the trailing end of the longest pole. (b) While loading and unloading materials, roadways shall
not be blocked unless approved traffic control is used. (c) When hauling poles during darkness, illuminated
warning devices shall be attached to the trailing end of the
longest pole in accordance with the state of Washington motor
vehicle code. (d) Framing. During framing operations, employees must
not work under a pole or a structure suspended by a crane,
A-frame or similar equipment unless the pole or structure is
adequately supported. (5) Tag lines. When necessary to control loads, tag
lines or other approved devices shall be used. (6) Oil filled equipment. During construction or repair
of oil filled equipment, the oil may be stored in temporary
containers other than those required by WAC 296-155-270, such
as pillow tanks. (7) Storage of tools and materials. All tools and
materials shall be stored in a safe and orderly manner in
yards for equipment and other areas.
[Statutory Authority: RCW 49.17.010, [49.17].040, [49.17].050
and [49.17].060. 98-07-009, § 296-45-315, filed 3/6/98,
effective 5/6/98.] (1) General. Only qualified employees may work on or
with exposed energized lines or parts of equipment. Only
qualified employees may work in areas containing unguarded,
uninsulated energized lines or parts of equipment operating at
50 volts or more. Electric lines and equipment shall be
considered and treated as energized unless the provisions of
WAC 296-45-175 through 296-45-17565 or 296-45-335 have been
followed. (2) Except as provided in subsection (3) of this section,
at least two qualified employees shall be present while the
following types of work are being performed: (a) Installation, removal, or repair of lines that are
energized at more than 600 volts; (b) Installation, removal, or repair of deenergized lines
if an employee is exposed to contact with other parts
energized at more than 600 volts; (c) Installation, removal, or repair of equipment, such
as transformers, capacitors, and regulators, if an employee is
exposed to contact with parts energized at more than 600
volts; (d) Work involving the use of mechanical equipment, other
than insulated aerial lifts, near parts energized at more than
600 volts; and (e) Other work that exposes an employee to electrical
hazards greater than or equal to those posed by operations
that are specifically listed in subsection (2)(a) through (d)
of this section. (a) When re-fusing circuits or equipment with a hot
stick. (b) When operating switches by means of operating handle
or switch sticks. (c) When installing or removing a hot line clamp
connection with an approved hot stick on a single-phase line
or apparatus, providing that the connection or disconnection
does not interrupt or pick up a load. (d) When installing or removing by hot stick simple load
metering devices provided the connection does not interrupt or
pickup load. (e) Emergency repairs to the extent necessary to
safeguard the general public. (4) "Minimum approach distances." The employer shall
ensure that no employee approaches or takes any conductive
object closer to exposed energized parts than set forth in
Table 1 through Table 4, unless: The employee is insulated from the energized part
(insulating gloves or insulating gloves and sleeves worn in
accordance with subsection (6) of this section are considered
insulation of the employee only with regard to the energized
part upon which work is being performed); or The energized part is insulated from the employee and
from any other conductive object at a different potential. (a) Before any work is performed, the location of
energized lines and their condition, the location and
condition of energized equipment, the condition of the poles,
the location of circuits and equipment including power
communication lines, CATV and fire alarm circuits, shall be
determined as shall any other particular hazard of a
particular work site. (b) No work shall be performed on energized lines or
parts until the voltage of such equipment and lines is
determined. (6) Type of insulation. If the employee is to be
insulated from energized parts by the use of insulating gloves
(under subsection (4) of this section), insulating sleeves
shall also be used. However, insulating sleeves need not be
used under the following conditions: (a) If exposed energized parts on which work is not being
performed are insulated from the employee; and (b) If such insulation is placed from a position not
exposing the employee's upper arm to contact with other
energized parts. (7) Working position. The employer shall ensure that
each employee, to the extent that other safety-related
conditions at the worksite permit, works in a position from
which a slip or shock will not bring the employee's body into
contact with exposed, uninsulated parts energized at a
potential different from the employee. (8) Making connections. The employer shall ensure that
connections are made as follows: (a) In connecting deenergized equipment or lines to an
energized circuit by means of a conducting wire or device, an
employee shall first attach the wire to the deenergized part; (b) When disconnecting equipment or lines from an
energized circuit by means of a conducting wire or device, an
employee shall remove the source end first; and (c) When lines or equipment are connected to or
disconnected from energized circuits, loose conductors shall
be kept away from exposed energized parts. (9) Rubber gloves can only be used on 5,000 volts or less
between phases. (10) It shall not be permissible to consider one part of
a high voltage switch or disconnect as deenergized for the
purpose of doing work on it if the remainder of the switch or
disconnect remains energized unless approved barriers are
erected which will prevent employees who are doing the work on
such equipment from coming in direct contact with the
energized parts. (11) Conductor support tools such as link sticks, strain
carriers, and insulator cradles may be used: Provided, That
the clear insulation is at least as long as the insulator
string or the minimum distance specified in Table 1 for the
operating voltage. (12) Apparel. (a) When work is performed within reaching distance of
exposed energized parts of equipment, the employer shall
ensure that each employee removes or renders nonconductive all
exposed conductive articles, such as key or watch chains,
rings, or wrist watches or bands, unless such articles do not
increase the hazards associated with contact with the
energized parts. (b) The employer shall train each employee who is exposed
to the hazards of flames or electric arcs in the hazards
involved. (c) The employer shall ensure that each employee who is
exposed to the hazards of flames or electric arcs does not
wear clothing that, when exposed to flames or electric arcs,
could increase the extent of injury that would be sustained by
the employee. (13) Fuse handling. When fuses must be installed or
removed with one or both terminals energized at more than 300
volts or with exposed parts energized at more than 50 volts,
the employer shall ensure that tools or gloves rated for the
voltage are used. When expulsion-type fuses are installed
with one or both terminals energized at more than 300 volts,
the employer shall ensure that each employee wears eye
protection meeting the requirements of WAC 296-45-25505(1),
uses a tool rated for the voltage, and is clear of the exhaust
path of the fuse barrel. (14) Covered (noninsulated) conductors. The requirements
of this section which pertain to the hazards of exposed live
parts also apply when work is performed in the proximity of
covered (noninsulated) wires. (15) Noncurrent-carrying metal parts. Noncurrent-carrying metal parts of equipment or devices, such
as transformer cases and circuit breaker housings, shall be
treated as energized at the highest voltage to which they are
exposed, unless the employer inspects the installation and
determines that these parts are grounded before work is
performed. (16) Opening circuits under load. Devices used to open
circuits under load conditions shall be designed to interrupt
the current involved.
[Statutory Authority: RCW 49.17.010, 49.17.040, 49.17.050,
and 49.17.060. 03-17-071, § 296-45-325, filed 8/19/03,
effective 11/1/03. Statutory Authority: RCW 49.17.040. 99-09-080, § 296-45-325, filed 4/20/99, effective 8/1/99. Statutory Authority: RCW 49.17.010, [49.17].040, [49.17].050
and [49.17].060. 98-07-009, § 296-45-325, filed 3/6/98,
effective 5/6/98.] (1) General. (a) Before elevated structures and adjacent structures,
such as poles or towers of the adjacent supporting poles,
structures, and conductor supporting hardware, are subjected
to such stresses as climbing or the installation or removal of
equipment may impose, the employer shall ascertain that the
structures are capable of sustaining the additional or
unbalanced stresses. If the pole or other structure cannot
withstand the loads which will be imposed, it shall be braced
or otherwise supported so as to prevent failure. (c) When a pole is set, moved, or removed near an exposed
energized overhead conductor, the employer shall ensure that
each employee wears electrical protective equipment or uses
insulated devices when handling the pole and that no employee
contacts the pole with uninsulated parts of his or her body. (d) To protect employees from falling into holes into
which poles are to be placed, the holes shall be attended by
employees or physically guarded whenever anyone is working
nearby. (2) Installing and removing overhead lines. The
following provisions apply to the installation and removal of
overhead conductors or cable. (a) The employer shall use the tension stringing method,
barriers, or other equivalent measures to minimize the
possibility that conductors and cables being installed or
removed will contact energized power lines or equipment. (b) When conductors are being strung in or removed, they
shall be kept under positive control to prevent accidental
contact with energized circuit. (c) The protective measures required by WAC 296-45-375(10)(c) for mechanical equipment shall also be
provided for conductors, cables, and pulling and tensioning
equipment when the conductor or cable is being installed or
removed close enough to energized conductors that any of the
following failures could energize the pulling or tensioning
equipment or the wire or cable being installed or removed: (i) Failure of the pulling or tensioning equipment; (ii) Failure of the wire or cable being pulled; or (iii) Failure of the previously installed lines or
equipment. (d) (( (e) Before lines are installed parallel to existing
energized lines, the employer shall make a determination of
the approximate voltage to be induced in the new lines, or
work shall proceed on the assumption that the induced voltage
is hazardous. Unless the employer can demonstrate that the
lines being installed are not subject to the induction of a
hazardous voltage or unless the lines are treated as
energized, the following requirements also apply: (i) Each bare conductor shall be grounded in increments
so that no point along the conductor is more than 2 miles
(3.22 km) from a ground. (ii) The grounds required in subsection (2)(e)(i) of this
section shall be left in place until the conductor
installation is completed between dead ends. (iii) The grounds required in subsection (2)(e)(i) of
this section shall be removed as the last phase of aerial
cleanup. (iv) If employees are working on bare conductors, grounds
shall also be installed at each location where these employees
are working, and grounds shall be installed at all open
dead-end or catch-off points or the next adjacent structure. (v) If two bare conductors are to be spliced, the
conductors shall be bonded and grounded before being spliced. (f) Reel handling equipment, including pulling and
tensioning devices, shall be in safe operating condition and
shall be leveled and aligned. (g) Load ratings of stringing lines, pulling lines,
conductor grips, load-bearing hardware and accessories,
rigging, and hoists may not be exceeded. (h) Each pull must be snubbed or dead ended at both ends
before subsequent pulls. (3) Pulling lines and accessories shall be inspected
prior to each use and replaced or repaired when damaged or
when there is a reasonable basis to doubt the dependability of
such lines or accessories. (4) Conductor grips may not be used on wire rope, unless
the grip is specifically designed for this application. (5) Reliable communications, through two-way radios or
other equivalent means, shall be maintained between the reel
tender and the pulling rig operator. (6) The pulling rig may only be operated when it is safe
to do so. (8) Live-line bare-hand work is prohibited. (9) When winches, trucks, or tractors are being used to
raise poles, materials, to pull in wires, to pull slack or in
any other operation, there shall be an operator at the
controls unless the machinery or process is stopped. (10) Leadworkers shall designate an employee to give
signals when required. (11) Raising poles, towers or fixtures in the close
proximity of high voltage conductors shall be done under the
supervision of a qualified employee. (12) Employees shall not crawl over insulator strings but
shall use a platform or other approved device to work from
when making dead ends or doing other work beyond strings of
insulators, at such distance that they cannot reach the work
from the pole or fixture. While working on the platform or
other device, they shall be secured with safety straps or a
rope to prevent falling. The provision of this subsection
does not apply to extra high voltage bundle conductors when
the use of such equipment may produce additional hazard. Climbing over dead end assemblies is permissible only after
they have been completed and pinned in the final position. (13) Towers and structures. The following requirements
apply to work performed on towers or other structures which
support overhead lines. (a) The employer shall ensure that no employee is under a
tower or structure while work is in progress, except where the
employer can demonstrate that such a working position is
necessary to assist employees working above. (b) Tag lines or other similar devices shall be used to
maintain control of tower sections being raised or positioned,
unless the employer can demonstrate that the use of such
devices would create a greater hazard. (c) The loadline may not be detached from a member or
section until the load is safely secured. (d) No one must be permitted to remain in the footing
while equipment is being spotted for placement. (e) A designated employee must be utilized to determine
that required clearance is maintained in moving equipment
under or near energized lines. (14) All conductors, subconductors, and overhead ground
conductors must be bonded to the tower at any isolated tower
where it may be necessary to complete work on the transmission
line. (15) A transmission clipping crew shall have a minimum of
two structures clipped in between the crew and the conductor
being sagged. (( ((
[Statutory Authority: RCW 49.17.010, [49.17].040, [49.17].050
and [49.17].060. 98-07-009, § 296-45-385, filed 3/6/98,
effective 5/6/98.] (1) Access and working space. Sufficient access and
working space shall be provided and maintained about electric
equipment to permit ready and safe operation and maintenance
of such equipment. (b) That the configuration of the installation enables
employees to maintain the minimum approach distances required
by WAC 296-45-325(5) while they are working on exposed,
energized parts; and (c) That the precautions taken when work is performed on
the installation provide protection equivalent to the
protection that would be provided by access and working space
meeting ANSI C2-1997. (d) Precaution must be taken to prevent accidental
operation of relays or other protective devices due to
jarring, vibration, or improper wiring. (2) Draw-out-type circuit breakers. When draw-out-type
circuit breakers are removed or inserted, the breaker shall be
in the open position. The control circuit shall also be
rendered inoperative, if the design of the equipment permits. (3) Substation fences. Conductive fences around
substations (( (4) Guarding of rooms containing electric supply
equipment. (a) Rooms and spaces in which electric supply lines or
equipment are installed shall meet the requirements of
subsection (4)(b) through (e) of this section under the
following conditions: (i) If exposed live parts operating at 50 to 150 volts to
ground are located within 8 feet of the ground or other
working surface inside the room or space; (ii) If live parts operating at 151 to 600 volts and
located within 8 feet of the ground or other working surface
inside the room or space are guarded only by location, as
permitted under subsection (5)(a) of this section; or (iii) If live parts operating at more than 600 volts are
located within the room or space, unless: (A) The live parts are enclosed within grounded,
metal-enclosed equipment whose only openings are designed so
that foreign objects inserted in these openings will be
deflected from energized parts; or (B) The live parts are installed at a height above ground
and any other working surface that provides protection at the
voltage to which they are energized corresponding to the
protection provided by an 8-foot height at 50 volts. (b) The rooms and spaces shall be so enclosed within
fences, screens, partitions, or walls as to minimize the
possibility that unqualified persons will enter. (c) Signs warning unqualified persons to keep out shall
be displayed at entrances to the rooms and spaces. (d) Entrances to rooms and spaces that are not under the
observation of an attendant shall be kept locked. (e) Unqualified persons may not enter the rooms or spaces
while the electric supply lines or equipment are energized. (5) Guarding of energized parts. (a) Guards shall be provided around all live parts
operating at more than 150 volts to ground without an
insulating covering, unless the location of the live parts
gives sufficient horizontal or vertical or a combination of
these clearances to minimize the possibility of accidental
employee contact. (ii) That each employee is isolated from energized parts
at the point of closest approach; and (iii) That the precautions taken when work is performed
on the installation provide protection equivalent to the
protection that would be provided by horizontal and vertical
clearances meeting ANSI C2-1997. (b) Except for fuse replacement and other necessary
access by qualified persons, the guarding of energized parts
within a compartment shall be maintained during operation and
maintenance functions to prevent accidental contact with
energized parts and to prevent tools or other equipment from
being dropped on energized parts. (c) When guards are removed from energized equipment,
barriers shall be installed around the work area to prevent
employees who are not working on the equipment, but who are in
the area, from contacting the exposed live parts. (6) Substation entry. (a) Upon entering an attended substation, each employee
other than those regularly working in the station shall report
his or her presence to the employee in charge in order to
receive information on special system conditions affecting
employee safety. (b) The job briefing required by WAC 296-45-135 shall
cover such additional subjects as the location of energized
equipment in or adjacent to the work area and the limits of
any deenergized work area.
[Statutory Authority: RCW 49.17.010, [49.17].040, [49.17].050
and [49.17].060. 98-07-009, § 296-45-475, filed 3/6/98,
effective 5/6/98.]
Note 1:
This subsection applies to structures that support overhead electric power generation, transmission, and
distribution lines and equipment. It does not apply to portions of buildings, such as loading docks, to
electric equipment, such as transformers and capacitors, nor to aerial lifts. Requirements for fall
protection associated with walking and working surfaces are contained in WAC 296-155-245;
requirements for fall protection associated with aerial lifts are contained in chapter 296-155 WAC,
Part J-1.
Note 2:
Employees undergoing training are not considered "qualified employees" for the purposes of this
provision. Unqualified employees (including trainees) are required to use fall protection any time they
are more than 4 feet (1.2 m) above the ground.
(13) The following requirements apply to personal fall
arrest systems:
AMENDATORY SECTION(Amending WSR 98-07-009, filed 3/6/98,
effective 5/6/98)
WAC 296-45-315
Materials handling and storage.
(1)
General. Material handling and storage shall conform to the
requirements of chapter 296-24 WAC, Part D.
Note:
Requirements for the size of the working space are contained in WAC 296-45-475(1) and 296-45-48515.
(3) Prior to unloading steel, poles, crossarms and
similar materials, the load shall be thoroughly examined to
determine if the load has shifted, binders or stakes have
broken or the load is otherwise hazardous to employees. The
hoist rope shall not be wrapped around the load. This
provision shall not apply to electric construction crews when
setting or removing poles.
AMENDATORY SECTION(Amending WSR 03-17-071, filed 8/19/03,
effective 11/1/03)
WAC 296-45-325
Working on or near exposed energized
parts.
This section applies to work on exposed live parts, or
near enough to them, to expose the employee to any hazard they
present.
Note 1:
One employee will serve principally as a standby person who must be so located that they may
physically reach the other employee in the event of an accident either with their hand or with a hot
stick twelve feet or less in length. The standby will be so positioned as to be able to observe the other
employee, their bodily movements, and verbally warn of any impending dangers. In no case when
working in pairs will employees work simultaneously on energized wires or parts of different phases or
polarity;
Note 2:
When installing or removing a hot line clamp connection on a multiphase system, it is permissible for
the second employee to stand by at the lower controls of the aerial lift provided the connection or
disconnection does not interrupt or pick up load. The hot line clamp and connecting jumper must be
constructed so it cannot make contact with any other energized parts. The work must not be
performed above lines or apparatus energized at more than 600 V.
Note 3:
In cases of necessity the standby person may temporarily assist the other employee provided that they
both work on wires or parts of the same phase or polarity. Both employees shall so position
themselves so that the presence of the second person does not increase the hazard.
(3) The provisions of WAC 296-45-325(2) do not apply ((in
the following circumstances:)) to (a) through (e) of this
subsection. In addition to the requirements of subsection (4)
of this section, a qualified employee working under this
subsection (3), must position themselves so that he/she is
neither within reach of nor otherwise exposed to contact with
energized parts.
Note 1:
The hot line clamp and connecting jumper must be constructed so that it cannot make contact with
any other energized parts.
Note 2:
On a multiphase feed this applies only when one single-phase line or apparatus is present on the load
side.
Note 1:
WAC 296-45-475 (5)(a) and 296-45-48525(1) contain requirements for the guarding and isolation of
live parts. Parts of electric circuits that meet these two provisions are not considered as "exposed"
unless a guard is removed or an employee enters the space intended to provide isolation from the live
parts.
Note 2:
When an employee is required to work on or within reach of any unprotected conductors that are or
may become energized at more than 50 volts and less than 600 volts between phases, they shall take
the following precautions:
1:
They shall wear approved insulating gloves or insulating gloves and sleeves during the time they are
working on such conductor, or
2:
They shall cover, with approved devices, any adjacent unprotected conductor that could be touched by
any part of their body, and use insulated tools.
3:
Cables which are properly insulated for the voltages to which they are energized, shall be considered as
an effective barrier to protect the employees and Table 1 need not apply.
(5) Initial determination.
Note:
Clothing made from the following types of fabrics, either alone or in blends, is prohibited by this subsection, unless the
employer can demonstrate that the fabric has been treated to withstand the conditions that may be encountered or
that the clothing is worn in such a manner as to eliminate the hazard involved: Acetate, nylon, polyester, rayon.
(d) Workers shall wear clothing appropriate to the season
and the kind of work being performed. Shirts or jumpers must
have full length sleeves that are rolled down. Protective
hard hats and eye protection shall be worn when working on or
near live parts or while climbing poles.Table 1: AC Live Work Minimum Approach Distance
Distance to employee
Voltage in kilovolts
phase to phase*
Phase to ground
Phase to Phase
(m)
(ft-in)
(m)
(ft-in)
0 to 0.050
not specified
not specified
0.051 to 0.300
avoid contact
avoid contact
0.301 to 0.750
0.31
1-0
0.31
1-0
0.751 to 15
0.65
2-2
0.67
2-3
15.1 to 36.0
0.77
2-7
0.86
2-10
36.1 to 46.0
0.84
2-9
0.96
3-2
46.1 to 72.5
1.00**
3-3**
1.20
3-11
72.6 to 121
0.95**
3-2**
1.29
4-3
138 to 145
1.09
3-7
1.50
4-11
161 to 169
1.22
4-0
1.71
5-8
230 to 242
1.59
5-3
2.27
7-6
345 to 362
2.59
8-6
3.80
12-6
500 to 550
3.42
11-3
5.50
18-1
765 to 800
4.53
14-11
7.91
26-0
*For single-phase systems, use the highest voltage available.
For single-phase lines off three phase systems, use the
phase-to-phase voltage of the system.
**The 46.1 to 72.5 kV phase-to-ground 3-3 distance contains a
1-3 electrical component and a 2-0 inadvertent movement
component while the 72.6 to 121 kV phase-to-ground 3-2
distance contains a 2-2 electrical component and a 1-0
inadvertent movement component.
Note 1:
These distances take into consideration the highest switching surge an employee will be exposed to on
any system with air as the insulating medium and the maximum voltages shown.
Note 2:
The clear live-line tool distance shall equal or exceed the values for the indicated voltage ranges.
Note 3:
See Appendix B to this section for information on how the minimum approach distances listed in the
tables were derived.
AMENDATORY SECTION(Amending WSR 98-07-009, filed 3/6/98,
effective 5/6/98)
WAC 296-45-385
Overhead lines.
This section provides
additional requirements for work performed on or near overhead
lines and equipment.
Note:
Appendix C contains test methods that can be used in ascertaining whether a wood pole is capable of sustaining the
forces that would be imposed by an employee climbing the pole. This paragraph also requires the employer to
ascertain that the pole can sustain all other forces that will be imposed by the work to be performed.
(b) When poles are set, moved, or removed near exposed
energized overhead conductors, the pole may not contact the
conductors.If the conductors being installed or removed cross
over energized conductors in excess of 600 volts and if the
design of the circuit-interrupting devices protecting the
lines so permits, the automatic-reclosing feature of these
devices shall be made inoperative.)) When conductors being
installed or removed cross over energized conductors in excess
of 600 volts, rope nets or guard structures must be installed
unless provision is made to isolate or insulate the worker or
the energized conductor. Where the design of the
circuit-interrupting devices protecting the lines so permits,
the automatic-reclosing feature of these devices must be made
inoperative. In addition, the line being strung must be
grounded on either side of the crossover or considered and
worked as energized.
Note:
Examples of unsafe conditions include employees in locations prohibited by subsection (7) of this section, conductor
and pulling line hang-ups, and slipping of the conductor grip.
(7) While the conductor or pulling line is being pulled
(in motion) with a power-driven device, employees are not
permitted directly under overhead operations or on the cross
arm, except as necessary to guide the stringing sock or board
over or through the stringing sheave.(15))) (16) While on patrol at night and operating a
motor vehicle on public highways, there shall be two
employees, at least one of whom shall be a journey level
lineworker or otherwise qualified employee. If repair to line
or equipment is found to be of such nature as to require two
lineworkers, work shall not proceed until additional help has
been obtained provided that in cases of emergency where delay
would increase the danger to life, limb, or substantial
property, one employee may clear the hazard without
assistance.(16))) (17) Except during emergency restoration
procedures, work shall be discontinued when adverse weather
conditions would make the work hazardous in spite of the work
practices required by this section.
Note:
Thunderstorms in the immediate vicinity, high winds, snow storms, and ice storms are examples of adverse weather
conditions that are presumed to make this work too hazardous to perform, except under emergency conditions.
AMENDATORY SECTION(Amending WSR 98-07-009, filed 3/6/98,
effective 5/6/98)
WAC 296-45-475
Substations.
This section provides
additional requirements for substations and for work performed
in them.
Note:
Guidelines for the dimensions of access and working space about electric equipment in substations are contained
in American National Standard-National Electrical Safety Code, ANSI C2-1997. Installations meeting the
ANSI provisions comply with WAC 296-45-475(1). An installation that does not conform to this ANSI
standard will, nonetheless, be considered as complying with WAC 296-45-475(1) if the employer can
demonstrate that the installation provides ready and safe access based on the following evidence:
(a) That the installation conforms to the edition of ANSI
C2 that was in effect at the time the installation was made;shall)) must be grounded. When a substation
fence ((is)) must be expanded or ((a section is)) removed((,))
fence ((grounding)) continuity ((shall)) must be
maintained((,)) and bonding ((shall)) must be used to prevent
electrical discontinuity. A temporary fence affording similar
protection when the site is unattended, must be provided.
Adequate interconnection with ground must be maintained
between temporary fence and permanent fence.
Note:
Guidelines for the dimensions of clearance distances about electric equipment in substations are contained in
American National Standard-National Electrical Safety Code, ANSI C2-1997. Installations meeting the ANSI
provisions comply with subsection (5)(a) of this section. An installation that does not conform to this ANSI
standard will, nonetheless, be considered as complying with subsection (5)(a) of this section if the employer can
demonstrate that the installation provides sufficient clearance based on the following evidence:
(i) That the installation conforms to the edition of ANSI
C2 that was in effect at the time the installation was made;